Building Process

Typical Construction Time

HOMES UP TO 3000 SQ FT

6 months from construction start

HOMES 3000-5500 SQ FT

7+ months from construction start

HOMES 5500+ SQ FT

9+ months from construction start

Design Phase (2 weeks)

  • Develop design criteria and subdivision requirements (if applicable)
  • Draw floor plan or select an existing plan
  • Draw roof plan, elevations, electrical plans, and site plan
  • Obtain loan pre-approval

Contract & Specifications (2 weeks)

  • Specify unique products or features to be used in home
  • Determine pricing on home based on plan design and features
  • Sign contract

Pre-Construction (6 weeks)

  • Submit contract documents to lender for construction loan
  • Geotechnical reports on soil
  • Foundation engineering
  • HOA Submittal
  • Obtain permits…..(City of Houston – add 45 days) (City of Conroe – add 15 days)

Construction

  • Site preparation / foundation
  • Framing and mechanicals
  • Drywall, trim carpentry, cabinets
  • Completion of Flooring, paint, and fixtures
  • Landscaping and final clean-up
  • Final walk / move-in

Permanent Loan Processing (45 days)

  • Submit contract documents to lender for permanent loan
  • Survey property
  • Appraise project
  • Closing documents